- PERSONAL COMPUTER PROJECT MANAGEMENT
-
-
-
-
-
-
-
-
-
-
- PREPARED BY:
-
- Len Shepard
- 444 North 3rd Street, Suite 201
- Sacramento, CA 95814
- (916) 446-1615
-
-
-
-
-
-
-
-
-
-
- November 21, 1984
-
-
-
-
-
-
-
-
-
-
-
- è
-
- TABLE OF CONTENTS
-
-
- Page
-
- I. INTRODUCTION
-
- A. PREPARATION
-
- 1. The Node Network 1
-
- 2. The Input Worksheet 1
-
- B. ENTERING THE BASE FILE 2
-
- C. SYSTEM GENERATED FILES 2
-
- D. CHANGING THE INPUT FILE 2
-
-
- II. SAMPLE SESSION RUNNING PCPM 3
-
- A. Creation of Sample File 4
-
- 1 - INFORMATION 4
- 2 - ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE 5
- 3 - ENTER/CHANGE INPUT FILE 7
-
- Change Project Title 7
- Input/Add Activities 9
- Delete Activities 10
- Change Activity Data 12
- Change Time Period Units 14
- Change Start Date 15
- Inspect Input File 16
- Check Node Connections 18
- Sort and File Input 19
- Filing Changes 20
-
- 4 - CREATE/CHANGE HOLIDAYS 22
- 5 - PERFORM CRITICAL PATH ANALYSIS 24
- 6 - PERFORM CASH FLOW ANALYSIS 25
- 7 - PRODUCE BAR CHARTS 26
- 8 - SORT OUTPUT 28
- 9 - EXTRACT OUTPUT BY SUBCONTRACTOR 30
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- Page
- ____
-
- 10 - CHECK NODE NUMBERS 31
- 11 - PRECEDENCE OR SUCCEEDENCE DISPLAY 32
- 12 - CONVERT WORKING DAYS TO PROJECT DAYS 33
- 13 - GENERATE CURRENT COST REPORT 34
- 14 - CHANGE ALL NODE NUMBERS 35
- 15 - CONSOLIDATE UPDATE FILES TO INPUT FILES 36
-
- EXITING PCPM 37
-
- III. SYSTEM ERRORS 38
-
-
- IV. OUTPUT
-
- A. Primary 39
-
- B. Cash Flow Analysis 39
-
- C. Barchart 39
-
- D. Current Cost Report 39
-
- E. Preceeder or Succeeder Display 39
-
- V. APPENDIX
-
- A. Sample Input Form 40
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 1 USER'S MANUAL
-
-
-
- I. INTRODUCTION
-
-
- PCPM is a system of interactive programs for project management using
- the critical path method. The system is designed to handle all
- necessary functions internally or allow the more sophisticated user to
- build and modify files on his/her own by making use of system editing
- software. PCPM is menu-driven, that is, a menu of available options is
- displayed to the terminal for the user to choose the desired option.
- When that particular function has been completed, PCPM will again
- display the menu.
-
- A. PREPARATION
-
- 1. The_Node_Network
-
- To use PCPM the user must first have constructed a node network
- representation of the project. Each activity must have a
- description of up to 30 characters, a duration (time), and node
- numbers.
-
- The node network numbering must be performed in a specific
- fashion. Each node is assigned an integer number from 1 to
- 1000 and nodes are numbered in ascending order with the first
- node having the lowest number and the last node having the
- highest number. The "from" node for each activity must be less
- than (and not equal to) the "to" node for that activity. Note
- that not all numbers between the start and finish have to be
- used; in fact, spacing should be maintained to allow for
- future schedule changes.
-
- 2. The_Input_Worksheet
-
- Before input at the terminal is attempted, it is helpful to
- make an input worksheet. Enter the information from the node
- network. (See samples in the appendix).
-
- Optional entries for each activity are the report finish date,
- percent complete, subcontractor name/code or other comment, and
- activity cost.
-
- Any report finish date entered must be "legal". To be legal a
- date can not fall on a weekend or holiday when working days is
- the unit of time being used. Also, a legal date can not be
- prior to the start date of the project.
-
- PCPM may be run using any unit of time the user specifies. It
- is, however, up to the user to maintain consistency of input.
- Examples of possibilites are:
-
- Working days (does include weekends but not holidays).
-
- Calendar days (does not include holidays).
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 2 USER'S MANUAL
-
-
-
- Weeks (activity duration must be converted by the
- user - e.g., 10 days duration should be entered as 2).
-
- B. ENTERING_THE_BASE_FILE
-
- Using PCPM, a sample input file such as that on pages 4-5 can be
- created. Other functions, including creation of a holiday file,
- critical path and cash flow analyses, and sorting output are also
- performed by using PCPM.
-
- The user is guided interactively through each option of the menu.
- After each option is complete, the system returns to the menu.
-
- C. SYSTEM_GENERATED_FILES
-
- Accessory files to the input file are created by the system based
- upon the input file. It is, therefore, important that this file be
- accurately entered. In general, the existence of system created
- files can be ignored by the user. They are merely cogs in the
- machinery that allows PCPM to run. The following information is
- included to satisfy the more curious users.
-
- As options of the Main Menu are performed, the system creates
- accessory files. These accessory files are described with the base
- file name and a three letter extension. For example, when
- utilizing OPTION 4 - CREATE/CHANGE HOLIDAYS, the system creates
- (automatically) a file denoted by BASEFILENAME.HOL.
-
- Here are some of the system created files for example file "LLP":
-
- LLP.CFA - output file for cash flow analysis
- LLP.CPM - input file for option 5 (main file)
- LLP.CST - output file for current cost report
- LLP.DAY - file of working vs. project days from Option 12
- LLP.HOL - file of holidays created by Option 3
- LLP.LGS - file of data for sorts used by Options 6,7,8, & 9
- LLP.PRE - output file containing predecessor printout
- LLP.SRT - sorted output file created by option 8
- LLP.SUC - output file containing successor printout
- LLP.UPD - updated input file created by Option 5
-
- D. CHANGING_THE_INPUT_FILE
-
-
- Changing the input file is easily done by changing node
- connections, durations, and/or adding report finish dates. Once
- the modifications to the input file are made, rerun Option 5. The
- system will quickly calculate the new durations, critical path, and
- completion times.
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 3 USER'S MANUAL
-
-
- II. SAMPLE SESSION RUNNING PCPM
-
- The following is a sample of what the completed input file, called LLP,
- looks like.
-
- P&L CONSTRUCTION PROJECT
- 1,MOBILIZATION,500,510,2,1,0,0,0,1,0
- 2,GRADE & CLEAR SITE,510,520,5,4,0,0,0,2,0
- 3,REBAR PIERS,520,530,5,9,0,0,0,3,0
- 4,POUR PIERS,530,550,5,0,0,0,0,4,0
- 5,EXCAVATE FOUNDATIONS,550,560,8,8,0,0,0,5,0
- 6,REBAR FOUNDATIONS,560,570,5,5,0,0,0,6,0
- 7,ANCHOR BOLTS,570,580,2,2,0,0,0,7,0
- 8,POUR & CURE FOUNDATIONS,580,585,5,5,0,0,0,8,0
- 9,STRUCTURAL STEEL,585,587,10,10,0,0,0,9,0
- 10,DECK FILL CONC.,590,600,15,15,0,0,0,10,0
- 11,WELD STRUCTURAL,587,595,20,20,0,0,0,11,0
- 12,FIRE PROOFING,620,625,5,5,0,0,0,12,0
- 13,PRECAST PANELS,625,650,20,20,0,0,0,13,0
- 14,P.M. FRAMES,600,790,2,2,0,0,0,14,0
- 15,WALL FRAMING,600,790,20,20,0,0,0,15,0
- 16,SHEET METAL DUCTWORK,600,955,40,40,0,0,0,16,0
- 17,ELEC. RGH. IN,620,640,10,10,0,0,0,17,0
- 18,MAIN ELEC PANEL,640,790,10,10,0,0,0,18,0
- 19,PLUMING RGH IN,620,630,5,5,0,0,0,19,0
- 20,POUR S.O.G.,630,790,8,8,0,0,0,20,0
- 21,STAIRCASES,585,590,25,25,0,0,0,21,0
- 22,PLUMB. TOP OUT,630,890,10,10,0,0,0,22,0
- 23,ELEC. PULL WIRE & POWER,640,760,10,10,0,0,0,23,0
- 24,ELEC. FIXTURES/SWITCHES/PLUGS,760,960,5,5,0,0,0,24,0
- 25,STAIR FILL,597,710,10,10,0,0,0,25,0
- 26,INSULATION,790,800,2,2,0,0,0,1,0
- 27,DRYWALL,800,810,10,10,0,0,0,27,0
- 28,CERAMIC TILE,810,850,20,20,0,0,0,28,0
- 29,PAINT INTERIOR,810,860,10,10,0,0,0,29,0
- 30,DUMMY,860,870,0,0,0,0,0,30,0
- 31,STAIN DOORS,870,920,5,5,0,0,0,31,0
- 32,FINISH HARDWARE,920,960,5,5,0,0,0,32,0
- 33,METAL SIDING,650,890,2,2,0,0,0,33,0
- 34,ACCESS LADDER,950,960,1,1,0,0,0,34,0
- 35,REGISTERS & GRILLS,955,957,5,5,0,0,0,35,0
- 36,BALANCE H.V.A.C.,957,960,2,2,0,0,0,36,0
- 37,TOILET FIXTURES,850,910,5,5,0,0,0,37,0
- 38,TOILET PARTITIONS,910,940,2,2,0,0,0,38,0
- 39,PAINT STAIRS,710,960,3,3,0,0,0,39,0
- 40,CURBS & SIDEWALKS,650,960,5,5,0,0,0,40,0
- 41,FINAL CLEAN UP,960,970,2,2,0,0,0,41,0
- 42,DUMMY,600,620,0,0,0,0,0,42,0
- 43,ROOF HATCH,890,950,1,1,0,0,0,43,0
- 44,DUMMY,587,590,10,10,0,0,0,44,0
- 45,METAL DECK WELD,587,597,25,25,0,0,0,45,0
- 46,DUMMY,810,955,0,0,0,0,0,46,0
- 47,DUMMY,595,597,5,5,0,0,0,47,0
- 48,TOILET ACCESSORIES 0,940,960,2,2,0,0,0,48,0
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 4 USER'S MANUAL
-
-
- A. CREATION_OF_THE_INPUT_FILE_"LLP"
-
- The following is an actual session which you can duplicate on your
- computer. User responses are underlined. Remember to use UPPER CASE
- responses only. Comments and explanations are indicated by "/*".
-
- OPTION_1_-_INFORMATION
-
- A> PCPM
-
- Copyright information shows on the screen. Press the space bar to
- continue running PCPM.
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _1_
-
- INFORMATION ON THE PCPM SYSTEM
-
- PCPM is a menu driven Critical Path Method. Several utilities make
- this system a valuable tool for project management. Input can be done
- interactively in PCPM or be edited outside the PCPM system using EDLIN
- (IBM) or EDCOL (P&L).
-
- Using PCPM, you are guided interactively through each menu option. As
- each function is completed the screen returns to the main menu.
-
- Information and messages from the system are displayed in CAPS
- surrounded by "****". User responses should be made in UPPER CASE
- LETTERS only. Answers to prompts are provided in paranthesis, like
- (Y/N). The first answer (Y) is the default (<CR> key) answer.
-
- For detailed information refer to the PCPM USERS MANUAL. If further
- assistance is needed, call (916) 446-1613.
-
- Hit ENTER when you are ready to return to the main menu. <CR>
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 5 USER'S MANUAL
-
-
-
- OPTION_2_-_ENTER/CHANGE_SUBCONTRACTOR/COMMENT_FILE
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER 2
-
- Enter the name of the input file [.CPM] ? LLP
-
- Project: P&L CONSTRUCTION File: LLP.CPM
- Time Period Units: WORKING DAYS Sub. Codes: 48 Start Date: 070183
-
- SUBCONTRACTOR/COMMENT CODES
-
- Add, Change, Delete 1 WILSON 17 MACFORD 33 KRENCHIK
- or Quit (A/C/D/Q) ? D 2 JONES 18 MCCALL 34 LEACH
- 3 MILLER 19 TRAMMEL 35 FREEHAN
- Enter Code number 4 ARCHS 20 WHITE 36 TRESH
- or 0 to exit ? 24 5 LEMON 21 CABELL 37 WERST
- 6 BUGMAN 22 BROOK 38 LOLICH
- Enter Code number 7 SHECK 23 GIBSON 39 BUNNING
- or 0 to exit ? 0 8 WILLIS 24 GENET 40 MCLAIN
- 9 MEAD 25 KALINE 41 NORTHRUP
- 10 KNOUS 26 WILSON 42 STANLEY
- 11 HOM 27 PARR 43 OYLER
- 12 HEDIN 28 MORRIS 44 CASH
- 13 ROBER 29 BEREN 45 WOCKFUSS
- 14 MAST 30 WILCOX 46 GRUBB
- 15 JONEY 31 LOPEZ 47 COBB
- 16 FURRER 32 BAIR 48 GRENBERG
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 6 USER'S MANUAL
-
-
-
- Project: P&L CONSTRUCTION File: LLP.CPM
- Time Period Units: WORKING DAYS Sub. Codes: 48 Start Date: 070183
-
- SUBCONTRACTOR/COMMENT CODES
-
- Add, Change, Delete 1 WILSON 17 MACFORD 33 KRENCHIK
- or Quit (A/C/D/Q) ? C 2 JONES 18 MCCALL 34 LEACH
- 3 MILLER 19 TRAMMEL 35 FREEHAN
- Enter Code number 4 ARCHS 20 WHITE 36 TRESH
- or 0 to exit ? 8 5 LEMON 21 CABELL 37 WERST
- 6 BUGMAN 22 BROOK 38 LOLICH
- Enter New Name/Comment 7 SHECK 23 GIBSON 39 BUNNING
- WILLS 8 WILLIS 24 40 MCLAIN
- 9 MEAD 25 KALINE 41 NORTHRUP
- Enter Code number 10 KNOUS 26 WILSON 42 STANLEY
- or 0 to exit ? 0 11 HOM 27 PARR 43 OYLER
- 12 HEDIN 28 MORRIS 44 CASH
- 13 ROBER 29 BEREN 45 WOCKFUSS
- 14 MAST 30 WILCOX 46 GRUBB
- 15 JONEY 31 LOPEZ 47 COBB
- 16 FURRER 32 BAIR 48 GRENBERG
-
- Project: P&L CONSTRUCTION File: LLP.CPM
- Time Period Units: WORKING DAYS Sub. Codes: 48 Start Date: 070183
-
- SUBCONTRACTOR/COMMENT CODES
-
- Add, Change, Delete 1 WILSON 17 MACFORD 33 KRENCHIK
- or Quit (A/C/D/Q) ? Q 2 JONES 18 MCCALL 34 LEACH
- 3 MILLER 19 TRAMMEL 35 FREEHAN
- File Changes or Quit 4 ARCHS 20 WHITE 36 TRESH
- (F/Q) F 5 LEMON 21 CABELL 37 WERST
- 6 BUGMAN 22 BROOK 38 LOLICH
- 7 SHECK 23 GIBSON 39 BUNNING
- 8 WILLS 24 40 MCLAIN
- 9 MEAD 25 KALINE 41 NORTHRUP
- 10 KNOUS 26 WILSON 42 STANLEY
- 11 HOM 27 PARR 43 OYLER
- 12 HEDIN 28 MORRIS 44 CASH
- 13 ROBER 29 BEREN 45 WOCKFUSS
- 14 MAST 30 WILCOX 46 GRUBB
- 15 JONEY 31 LOPEZ 47 COBB
- 16 FURRER 32 BAIR 48 GRENBERG
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 7 USER'S MANUAL
-
-
-
- OPTION_3_-_ENTER/CHANGE_INPUT
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER 3
-
- Enter the name of the input file [.CPM] ? LLP
- 10 20 30 40 **** INPUT FILE READ ****
-
- INPUT_OPTION_1_-_CHANGE_TITLE
-
- Project: P&L CONSTRUCTION File: LLP.CPM
- Time Period Units: WORKING DAYS Activities: 48 Start Date: 070183
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- Enter number of the modification desired 1
-
- **** PRESENT TITLE IS P&L CONSTRUCTION
- ENTER NEW TITLE ? P&L_CONSTRUCTION_PROJECT
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 8 USER'S MANUAL
-
-
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: WORKING DAYS Activities: 48 Start Date: 070183
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- **** BE SURE TO FILE ANY CHANGES IF YOU WANT THEM ****
-
- /* This message appears as a reminder to file the
- changes you've just made before exiting the
- modification menu. It is not necessary to file
- changes after each menu option--only before
- returning to the Main Menu.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 9 USER'S MANUAL
-
-
-
- INPUT_OPTION_2_-_INPUT/ADD_ACTIVITIES
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: WORKING DAYS Activities: 48 Start Date: 070183
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- Enter number of the modification desired 2
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: WORKING DAYS Activities: 48 Start Date: 070183
-
- SUBCONTRACTOR/COMMENT CODES **** ACTIVITY 49 ****
- 1 WILSON 17 MACFORD 33 KRENCHIK Enter Description
- 2 JONES 18 MCCALL 34 LEACH ? ADDITION
- 3 MILLER 19 TRAMMEL 35 FREEHAN Enter FROM node ? 180
- 4 ARCHS 20 WHITE 36 TRESH Enter TO node ? 190
- 5 LEMON 21 CABELL 37 WERST Enter Estimated Time ? 4
- 6 BUGMAN 22 BROOK 38 LOLICH Enter finish date (MMDDYY) ? 0
- 7 SHECK 23 GIBSON 39 BUNNING Enter percent complete (###) ? 0
- 8 WILLS 24 40 MCLAIN Enter Subcontractor/Comment code ? 7
- 9 MEAD 25 KALINE 41 NORTHRUP Enter activity cost ($) ? 0
- 10 KNOUS 26 WILSON 42 STANLEY
- 11 HOM 27 PARR 43 OYLER Enter more activities (Y/N) ? N
- 12 HEDIN 28 MORRIS 44 CASH
- 13 ROBER 29 BEREN 45 WOCKFUSS
- 14 MAST 30 WILCOX 46 GRUBB
- 15 JONEY 31 LOPEZ 47 COBB
- 16 FURRER 32 BAIR 48 GRENBERG
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 10 USER'S MANUAL
-
-
-
-
- INPUT_OPTION_3_-_DELETE_ACTIVITIES
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: WORKING DAYS Activities: 49 Start Date: 070183
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- **** BE SURE TO FILE ANY CHANGES IF YOU WANT THEM ****
-
- Enter number of the modification desired 3
-
- **** WHEN DELETING, START WITH THE LAST ACTIVITY FIRST
- FOR BEST RESULTS ****
- **** WHEN CHANGING INPUT, REFER TO THE ACTIVITY POSITION WHICH IS
- DISPLAYED IN THE INPUT INSPECTION ROUTINE ****
-
- Inspect the activity file (Y/N/#)
-
- /* Y If a "Y" response is given, the activity
- file is displayed, beginning with Activity
- Position #1.
-
- /* N If a "N" response is given, the system asks
- "Enter number of activity to change" (input
- the Activity Position Number you wish to modify.)
-
- /* # Responding with an activity position number will
- produce the inspection file, beginning with that
- number.
-
- Inspect the activity file (Y/N/#) 40
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 11 USER'S MANUAL
-
-
-
- ACT FROM TO ACT EST REPORT % SUB NAME ACT
- POS _DESCRIPTION NODE NODE TIME TIME FINISH DUN COMMENT COST
-
- 40 CURBS & SID 650 960 5 5 0 0 MCCLAIN $0
- 41 FINAL CLEAN 960 970 2 2 0 0 NORTHRUP $0
- 42 DUMMY 600 620 0 0 0 0 STANLEY $0
- 43 ROOF HATCH 890 950 1 1 0 0 OYLER $0
- 44 DUMMY 587 590 10 10 0 0 CASH $0
- 45 METAL DECK 587 597 25 25 0 0 WOCKFUSS $0
- 46 DUMMY 810 955 0 0 0 0 GRUBB $0
- 47 DUMMY 595 597 5 5 0 0 COBB $0
- 48 TOILET ACC 940 960 2 2 0 0 GRENBERG $0
- 49 ADDITION 180 190 4 4 0 0 SHECK $0
-
- Press ENTER to continue <CR>
-
- Enter position number of the activity to delete - 0 to exit ? 49
- Enter position number of the activity to delete - 0 to exit ? 0
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 12 USER'S MANUAL
-
-
-
- INPUT_OPTION_4_-_CHANGE_ACTIVITY_DATA
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: WORKING DAYS Activities: 48 Start Date: 070183
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- FILE CHANGES - 9
-
- **** BE SURE TO FILE ANY CHANGES IF YOU WANT THEM ****
-
- Enter number of the modification desired _4_
-
- Inspect the activity file (Y/N/#) 20
-
- ACT FROM TO ACT EST REPORT % SUB NAME ACT
- POS _DESCRIPTION NODE NODE TIME TIME FINISH DUN COMMENT COST
-
- 20 POUR S.O.G. 630 790 8 8 0 0 WHITE $0
- 21 STAIRCASES 585 590 25 25 0 0 CABELL $0
- 22 PLUB. TOP O 630 890 10 10 0 0 BROOK $0
- 23 ELEC. PULL 640 760 10 10 0 0 GIBSON $0
- 24 ELEC. FIXTU 760 960 5 5 0 0 GENERAL $0
- 25 STAIR FILL 597 710 10 10 0 0 KALINE $0
- 26 INSULATION 790 800 2 2 0 0 WILSON $0
- 27 DRYWALL 800 810 10 10 0 0 PARR $0
- 28 CERAMIC TIL 810 850 20 20 0 0 MORRIS $0
- 29 PAINT INTER 810 860 10 10 0 0 BEREN $0
- 30 DUMMY 860 870 0 0 0 0 WILCOX $0
- 31 STAIN DOORS 870 920 5 5 0 0 LOPEZ $0
- 32 FINISH HARD 920 960 5 5 0 0 BAIR $0
- 33 METAL SIDIN 650 890 2 2 0 0 KRENCHIK $0
- 34 ACCESS LADD 950 960 1 1 0 0 LEACH $0
- 35 REGISTERS & 955 957 5 5 0 0 FREEHAN $0
- 36 BALANCE H.V 957 960 2 2 0 0 TRESH $0
- 37 TOILET FIXT 850 910 5 5 0 0 WERST $0
-
- Press ENTER to continue, or Q to quit <CR>
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 13 USER'S MANUAL
-
-
-
-
- ACT FROM TO ACT EST REPORT % SUB NAME ACT
- POS _DESCRIPTION NODE NODE TIME TIME FINISH DUN COMMENT COST
-
- 38 TOILET PART 910 940 2 2 0 0 LOLICH $0
- 39 PAINT STAIR 710 960 3 3 0 0 BUNNING $0
- 40 CURBS & SID 650 960 5 5 0 0 MCCLAIN $0
- 41 FINAL CLEAN 960 970 2 2 0 0 NORTHRUP $0
- 42 DUMMY 600 620 0 0 0 0 STANLEY $0
- 43 ROOF HATCH 890 950 1 1 0 0 OYLER $0
- 44 DUMMY 587 590 10 10 0 0 CASH $0
- 45 METAL DECK 587 597 25 25 0 0 WOCKFUSS $0
- 46 DUMMY 810 955 0 0 0 0 GRUBB $0
- 47 DUMMY 595 597 5 5 0 0 COBB $0
- 48 TOILET ACC 940 960 2 2 0 0 GRENBERG $0
-
- Press ENTER to continue <CR>
-
- Enter pointer to activity to change 27
-
- DRYWALL 800 810 10 10 0 0 PARR 0
-
- Change DESC,FROM NODE,TO NODE,TIME,FINDAT,%,SUB CODE,COST,QUIT
- Enter ( D , FN , TN , T , F ,%, S , C , or Q) TN
- Enter the new TO node _870_
- _____
-
- DRYWALL 810 870 10 10 0 0 PARR 0
-
- Change DESC,FROM NODE,TO NODE,TIME,FINDAT,%,SUB CODE,COST,QUIT
- Enter ( D , FN , TN , T , F ,%, S , C , or Q) S
- Enter subcode number ? 10
-
- DRYWALL 810 870 10 10 0 0 KNOUS 0
- Change More Activities (Y/N/#) N
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 14 USER'S MANUAL
-
-
-
- INPUT_OPTION_5_-_CHANGE_TIME_PERIOD_UNITS
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: WORKING DAYS Activities: 48 Start Date: 070183
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- **** BE SURE TO FILE ANY CHANGES IF YOU WANT THEM ****
-
- Enter number of the modification desired _5_
- **** PRESENT TIME UNITS ARE WORKING DAYS ****
- Enter new time units CALENDAR_DAYS
- **** PCPM WILL OMIT HOLIDAYS BUT NOT WEEKENDS ****
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 15 USER'S MANUAL
-
-
-
- INPUT_OPTION_6_-_CHANGE_START_DATE
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: CALENDAR DAYS Activities: 48 Start Date: 070183
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- **** BE SURE TO FILE ANY CHANGES IF YOU WANT THEM ****
-
- Enter number of the modification desired _6_
- **** PRESENT START DATE IS 070183 ****
- Enter new start date in MMDDYY format ? 10483
-
- /*10483 would be January 4, 1983
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 16 USER'S MANUAL
-
-
-
- INPUT_OPTION_7_-_INSPECT_INPUT
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: CALENDAR DAYS Activities: 48 Start Date: 10483
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- Enter number of the modification desired 7
-
- PROJECT TITLE : P&L CONSTRUCTION PROJECT
- TIME UNITS : CALENDAR
- START DATE : 010483
-
- Press ENTER to continue, or Q to quit <CR>
-
- ACT FROM TO ACT EST REPORT % SUB NAME ACT
- POS _DESCRIPTION NODE NODE TIME TIME FINISH DUN COMMENT COST
-
- 1 MOBILIZATION 500 510 2 2 0 0 WILSON $0
- 2 GRADE & CLEA 510 520 5 5 0 0 JONES $0
- 3 REBAR PIERS 520 530 5 5 0 0 MILLER $0
- 4 POUR PIERS 530 550 5 5 0 0 ARCHS $0
- 5 EXCAVATE FO 550 560 8 8 0 0 LEMON $0
- 6 REBAR FOUND 560 570 5 5 0 0 BUGMAN $0
- 7 ANCHOR BOLT 570 580 2 2 0 0 SHECK $0
- 8 POUR & CURE 580 585 5 5 0 0 WILLIS $0
- 9 STRUCTURAL 585 587 10 10 0 0 MEAD $0
- 10 DECK FILL C 590 600 15 15 0 0 KNOUS $0
- 11 WELD STRUCT 587 595 20 20 0 0 HOM $0
- 12 FIRE PROOFI 620 625 5 5 0 0 HEDIN $0
- 13 PRECAST PAN 625 650 20 20 0 0 ROBER $0
- 14 P.M. FRAMES 600 790 2 2 0 0 MAST $0
- 15 WALL FRAMIN 600 790 20 20 0 0 JONEY $0
- 16 SHEET METAL 600 955 40 40 0 0 FURRER $0
- 17 ELEC. RGH. 620 640 10 10 0 0 MACFORD $0
- 18 MAIN ELEC 640 790 10 10 0 0 MCCALL $0
- 19 PLUMBING RG 620 630 5 5 0 0 TRAMMEL $0
-
- Press ENTER to continue, or Q to quit <CR>
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 17 USER'S MANUAL
-
-
-
- ACT FROM TO ACT EST REPORT % SUB NAME ACT
- POS _DESCRIPTION NODE NODE TIME TIME FINISH DUN COMMENT COST
-
- 20 POUR S.O.G. 630 790 8 8 0 0 WHITE $0
- 21 STAIRCASES 585 590 25 25 0 0 CABELL $0
- 22 PLUB. TOP O 630 890 10 10 0 0 BROOK $0
- 23 ELEC. PULL 640 760 10 10 0 0 GIBSON $0
- 24 ELEC. FIXTU 760 960 5 5 0 0 GENERAL $0
- 25 STAIR FILL 597 710 10 10 0 0 KALINE $0
- 26 INSULATION 790 800 2 2 0 0 WILSON $0
- 27 DRYWALL 800 870 10 10 0 0 KNOUS $0
- 28 CERAMIC TIL 810 850 20 20 0 0 MORRIS $0
- 29 PAINT INTER 810 860 10 10 0 0 BEREN $0
- 30 DUMMY 860 870 0 0 0 0 WILCOX $0
- 31 STAIN DOORS 870 920 5 5 0 0 LOPEZ $0
- 32 FINISH HARD 920 960 5 5 0 0 BAIR $0
- 33 METAL SIDIN 650 890 2 2 0 0 KRENCHIK $0
- 34 ACCESS LADD 950 960 1 1 0 0 LEACH $0
- 35 REGISTERS & 955 957 5 5 0 0 FREEHAN $0
- 36 BALANCE H.V 957 960 2 2 0 0 TRESH $0
- 37 TOILET FIXT 850 910 5 5 0 0 WERST $0
-
- Press ENTER to continue, or Q to quit <CR>
-
- ACT FROM TO ACT EST REPORT % SUB NAME ACT
- POS _DESCRIPTION NODE NODE TIME TIME FINISH DUN COMMENT COST
-
- 38 TOILET PART 910 940 2 2 0 0 LOLICH $0
- 39 PAINT STAIR 710 960 3 3 0 0 BUNNING $0
- 40 CURBS & SID 650 960 5 5 0 0 MCCLAIN $0
- 41 FINAL CLEAN 960 970 2 2 0 0 NORTHRUP $0
- 42 DUMMY 600 620 0 0 0 0 STANLEY $0
- 43 ROOF HATCH 890 950 1 1 0 0 OYLER $0
- 44 DUMMY 587 590 10 10 0 0 CASH $0
- 45 METAL DECK 587 597 25 25 0 0 WOCKFUSS $0
- 46 DUMMY 810 955 0 0 0 0 GRUBB $0
- 47 DUMMY 595 597 5 5 0 0 COBB $0
- 48 TOILET ACC 940 960 2 2 0 0 GRENBERG $0
-
- Press ENTER to continue <CR>
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 18 USER'S MANUAL
-
-
-
- INPUT_OPTION_8_-_CHECK_NODE_CONNECTIONS
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: CALENDAR DAYS Activities: 48 Start Date: 10483
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- **** BE SURE TO FILE ANY CHANGES IF YOU WANT THEM ****
-
- Enter number of the modification desired _8_
- **** QUIET - COMPUTER THINKING - CHECKING NODES ****
- **** START NODES O.K. ****
- **** END NODES O.K. ****
-
- Press ENTER to continue <CR>
-
- /* Checking node connections can also be accomplished
- using Option 5 of the Main Menu, "PERFORM CRITICAL PATH
- ANALYSIS".
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 19 USER'S MANUAL
-
-
-
- INPUT_OPTION_9_-_SORT_AND_FILE_INPUT
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: CALENDAR DAYS Activities: 48 Start Date: 10483
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- **** BE SURE TO FILE ANY CHANGES IN YOU WANT THEM ****
-
- Enter number of the modification desired 9
-
- **** SORTING 48 ACTIVITIES ******** SORT COMPLETE ****
- **** WRITING FILE TO DISK ****
- **** FILE LLP.CPM UPDATED ****
- **** READING SORTED FILE ****
- 10 20 30 40 **** INPUT FILE READ ****
-
- Press ENTER to continue <CR>
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 20 USER'S MANUAL
-
-
- INPUT_OPTION_0_-_EXIT_MODIFICATION
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: CALENDAR DAYS Activities: 48 Start Date: 10483
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- **** BE SURE TO FILE ANY CHANGES IF YOU WANT THEM ****
-
- Enter number of the modification desired _0_
- Last changes were not filed - Are you sure (Y/N) ? _N_
-
- /* Before exiting the Modification Menu and returning
- to the Main Menu, any changes made must be filed.
- If it is desired, the changes can be stored under a
- separate file name.
-
- INPUT_OPTION_10_-_FILE_CHANGES
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: CALENDAR Fa2S Activities: 48 Start Date: 10483
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- Enter number of the modification desired 10
-
- Use LLP.CPM as filename (Y/N) ? _Y_
- **** FILE LLP.CPM UPDATED ****
-
- /* If "N", System asks "Enter new filename".
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 21 USER'S MANUAL
-
-
-
-
- Project: P&L CONSTRUCTION PROJECT File: LLP.CPM
- Time Period Units: CALENDAR DAYS Activities: 48 Start Date: 10483
-
- INPUT MODIFICATION MENU
-
- EXIT MODIFICATION - 0
- CHANGE TITLE - 1
- INPUT/ADD ACTIVITIES - 2
- DELETE ACTIVITIES - 3
- CHANGE ACTIVITY DATA - 4
- CHANGE TIME PERIOD UNITS - 5
- CHANGE START DATE - 6
- INSPECT INPUT - 7
- CHECK NODE CONNECTIONS - 8
- SORT AND FILE INPUT - 9
- FILE CHANGES -10
-
- Enter number of the modification desired _0_
-
- /* System returns to Main Menu.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 22 USER'S MANUAL
-
-
-
- OPTION_4_-_CREATE/CHANGE_HOLIDAYS
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _4_
-
-
- **** THIS MODULE CREATES AND MANAGES HOLIDAY [.HOL] FILES ****
-
- Enter the name of the base data file ? LLP
- Enter holidays in MM,DD,YY format (0,0,0 if end) ? 2,21,83
- Enter holidays in MM,DD,YY format (0,0,0 if end) ? 5,30,83
- Enter holidays in MM,DD,YY format (0,0,0 if end) ? 7,3,83
- Enter holidays in MM,DD,YY format (0,0,0 if end) ? 9,5,83
- Enter holidays in MM,DD,YY format (0,0,0 if end) ? 11,11,83
- Enter holidays in MM,DD,YY format (0,0,0 if end) ? 11,24,83
- Enter holidays in MM,DD,YY format (0,0,0 if end) ? 0,0,0
-
- **** LIST OF HOLIDAYS FOR THE BASE DATA FILE LLP ****
-
- 1 February 21 1983
- 2 May 30 1983
- 3 July 3 1983
- 4 September 5 1983
- 5 November 11 1983
- 6 November 24 1983
-
- /* The holiday file can also be used to store any
- date on which no work was done--such as rain
- days, or strikes. Just enter the days as if
- they were holidays.
-
- Do you want to change, add, delete or quit (C/A/D/Q) _C_
-
- Enter number of holiday to change _3_
- Enter new date in MM,DD,YY format _7,4,83_
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 23 USER'S MANUAL
-
-
-
- **** LIST OF HOLIDAYS FOR THE BASE DATA FILE LLP ****
-
- 1 February 21 1983
- 2 May 30 1983
- 3 July 4 1983
- 4 September 5 1983
- 5 November 11 1983
- 6 November 24 1983
-
- Do you want to change, add, delete or quit (C/A/D/Q) _D_
-
- ENTER NUMBER OF HOLIDAY TO DELETE 6
-
- **** LIST OF HOLIDAYS FOR THE BASE DATA FILE LLP ****
-
- 1 February 21 1983
- 2 May 30 1983
- 3 July 4 1983
- 4 September 5 1983
- 5 November 11 1983
-
- Do you want to change, add, delete or quit (C/A/D/Q) _Q_
- File changes or Quit (F/Q) ? F
- **** FILENAME IS LLP.HOL ****
-
- /* The file is stored under BASEFILE.HOL and the system returns
- to Main Menu.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 24 USER'S MANUAL
-
-
-
- OPTION_5_-_PERFORM_CRITICAL_PATH_ANALYSIS
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _5_
-
- Enter the name of the input file [.CPM] ? _LLP_
- 10 20 30 40 **** INPUT FILE READ ****
- **** BYPASSING SORT ROUTINE ****
- The Output Filename is LLP.OUT O.K. (Y/N) ? Y
- Want to adjust for reported finish times (Y/N) ? Y
-
- /* A "N" ignores the report finish dates entirely.
-
- **** PROJECT LENGTH IS 140 WORKING DAYS ****
- **** THIS WILL TAKE 140 SECONDS IN REGULAR BASIC ****
- **** END DATE IS MAY2483 ****
- **** READING SUB CONTRACTORS ****
- **** OUTPUTTING ANALYSIS AND SORT FILE ****
-
- Want to create an updated schedule (Y/N) _Y_
- **** CAUTION: YOU MUST CONSOLIDATE UPDATE FILES BEFORE CALLING
- NEW OPTIONS ****
- **** FINISHED CPM - WRITING CRITICAL PATH LIST TO FILE ****
-
- /* An update file called LLP.UPD has been created.
-
- /* The Critical Path Analysis is complete. System now
- returns to Main Menu.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 25 USER'S MANUAL
-
-
-
-
- OPTION_6_-_PERFORM_CASH_FLOW_ANALYSIS
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _6_
-
- /* CFA calculates the monthly cash outlays for each activity
- throughout the project based on the schedule as calculated by
- Option 5. Costs can be calculated based on early or late start
- dates. Activities which have not yet incurred costs can be
- excluded.
-
- Enter the name of the input file [.CPM] ? _LLP_
- 10 20 30 40 **** INPUT FILE READ ****
-
- Want Early or Late Projection (E/L) ? _E_
- 10 20 30 40 **** LGS FILE READ ****
- **** NOW FIGURING DAYS - WILL TAKE 35 SECONDS IN REGULAR BASIC ****
- **** DAYS FIGURED - DISTRIBUTING COSTS AMONG MONTHS ****
- Name of output file is LLP.CFA O.K. (Y/N) ? Y
- Want to suppress zero-cost activities (Y/N) ?_Y_
- **** THINKING FINISHING ****
- **** LLP.CFA CREATED ****
-
- /* When the calculation is complete, the system returns to
- Menu. The sample Cash Flow Analysis, contained in output
- file LLP.CFA, is shown in the appendix.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 26 USER'S MANUAL
-
-
-
-
- OPTION_7_-_PRODUCE_BAR_CHARTS
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER 7
-
- Enter the name of the input file [.CPM] ? LLP
-
- **** INPUT FILE READ ****
- 10 20 30 40 **** LGS FILE READ ****
- **** CALCULATING DAYS ****
- Output File will be LLP.BAR O.K. (Y/N) ? Y
- Enter width for the chart. Enter defaults to 90 : <CR>
-
- /* The width for the barchart depends on the printer
- used and the number of days in the schedule. The
- width is divided into the schedule duration.
-
- Example:
-
- Project duration is 160 days. Entering a "90" will
- produce a barchart with activities represented in
- 1.78 day segments of time. This same schedule
- duration could produce a barchart represented by
- 2_day segments of time, if 80 is entered instead.
- Any number up to 95 is acceptable for barchart width.
-
- Want whole project or Portion (W/P) _P_
-
- /* For an example of a bar chart portion, see
- below.
-
- Will several portions be placed together (Y/N/HELP) _HELP_
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 27 USER'S MANUAL
-
-
-
-
- If you want to put several portions together, reply
- "Y". PCPM will space activities within each portion so
- the activities which extend from one portion to another
- will be in alignment when the barcharts are placed side
- by side.
- Will several portions be placed together (Y/N/Help) _Y_
-
- Enter beginning date in MMDDYY format 010483
-
- /* The date entered must be after the start of the
- project, before the end of the project, and a
- "real" date (for instance, if you are using
- working days, the date cannot be a holiday or
- weekend).
-
- Enter ending date (MMDDYY) or length in days 140
- **** EACH COLUMN WILL REPRESENT 1.56 CALENDAR DAYS ****
- *** FORMING BAR CHART ***
- Want another Bar Chart from the same run (N/Y) _N_
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 28 USER'S MANUAL
-
-
-
- OPTION_8_-_SORT_OUTPUT
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _8_
-
- /* Output can be requested with data arranged in a variety of
- sorts. The choices are listed in the sort menu.
-
- Enter the name of the input file [.CPM] _LLP_
- 10 20 30 40 **** INPUT FILE READ ****
-
- CHOICE OF SORTS
-
- NO SORT (RETURN TO MENU) - 0
- FROM NODES - 1
- TO NODES - 2
- ESTIMATED DURATIONS - 3
- ACTUAL DURATIONS - 4
- EARLY START DATES - 5
- LATE START DATES - 6
- EARLY FINISH DATES - 7
- LATE FINISH DATES - 8
- FLOAT (CRITICAL PATH) - 9
- SUBCONTRACTOR CODE/NAME - 10
-
- Enter the number of your sort choice ? _5_
-
- **** SORTING 48 ACTIVITIES - TAKES 16 SECONDS IN REGULAR BASIC ****
- **** FINISHED SORT - FIGURING DAYS - TAKES 35 SECONDS ****
- **** DAYS FIGURED - READING SUBCONTRACTORS ****
- **** FILE LLP.SBC READ - 48 SUBCONTRACTORS READ ****
- Output Filename is LLP.SRT O.K. (Y/N) ? Y
-
- /* In the example above, the activities will be sorted in
- order of early start dates.
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 29 USER'S MANUAL
-
-
-
- /* The subcontractor name sort option groups all subs with
- the same name together on the printout in code, not
- alphabetical order. If you wish each subcontractor
- to be listed on a separate printout, use Option 9
- of the Main Menu, "EXTRACT OUTPUT BY SUBCONTRACTOR."
-
- CHOICE OF SORTS
-
- NO SORT (RETURN TO MENU) - 0
- FROM NODES - 1
- TO NODES - 2
- ESTIMATED DURATIONS - 3
- ACTUAL DURATIONS - 4
- EARLY START DATES - 5
- LATE START DATES - 6
- EARLY FINISH DATES - 7
- LATE FINISH DATES - 8
- FLOAT (CRITICAL PATH) - 9
- SUBCONTRACTOR CODE/NAME - 10
-
- Enter the number of your sort choice ? 0
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 30 USER'S MANUAL
-
-
-
- OPTION_9_-_EXTRACT_OUTPUT_BY_SUBCONTRACTOR
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _9_
-
- PROGRAM TO EXTRACT SPECIFIC SUBCONTRACTOR PCPM OUTPUT
-
- Enter the name of the input file ? _LLP_
- **** INPUT FILE READ ****
- Enter subcontractor code (0 to exit) ? 10
- Output File is LLP.KNO, O.K. (Y/N) ? Y
- /* The data for each subcontractor selected appears in an
- output file named "filename.subname". (LLP.KNO in this
- example.) Each file contains only activities which are
- related to that contractor.
- /* The system returns to Main Menu.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 31 USER'S MANUAL
-
-
-
- OPTION_10_-_CHECK_NODE_NUMBERS
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _10_
-
- **** THIS MODULE PRINTS THE NODE NUMBERS USED IN A PROJECT ****
-
- /* This option is useful to avoid duplication of
- node numbers.
-
- Enter the name of the input file [.CPM] ? _LLP_
- **** INPUT FILE READ ****
- **** SORTING NODES ****
- **** THE FOLLOWING NODE NUMBERS ARE USED IN: LLP.CPM ****
- 500 510 520 530 550 560 570 580 585 587 590 597 600 620 625
- 630 640 650 710 760 790 800 810 850 860 870 910 920 940 950
- 955 957 960 970 **** CREATING FILE OF NODE NUMBERS ****
- **** LLP.NDS CREATED - USE OPTION 14 TO GLOBALLY CHANGE NODES ****
-
- **** CREATING FILE OF NODE NUMBERS - LLP.NDS ****
- **** FILE: LLP.NDS CREATED - USE OPTION 14 TO GLOBALLY
- CHANGE NODES ****
-
- Press ENTER to continue <CR>
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 32 USER'S MANUAL
-
-
-
- OPTION_11_-_GET_PRECEDENCE_OR_SUCCEEDENCE_DISPLAY
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _11_
-
- /* This option is used for diagnostic purposes to
- determine the cause of errors.
-
- Enter the name of the input file [.CPM] ? _LLP_
- 10 20 30 40 **** INPUT FILE READ ****
- Enter Predecessor or Successor (P/S) P
- **** SORTING 48 ACTIVITIES **** FINISHED SORTING ****
- **** THE FOLLOWING INDICATES HOW MANY PRECEEDOR S EXIST FOR EACH
- ACTIVITY ****
-
- 0 1 1 1 1 1 1 1 1 1 1 1 1 2 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 4 1
- 1 1 1 1 1 2 1 1 1 1 2 1 7
-
- /* These numbers may be ignored. Each number stands for the
- number of preceedors (or succeedors) each activity has.
- For the actual preceedors, refer to the output file
- "BASENAME.PRE".
-
- **** PRECEEDOR DISPLAY CREATED AND EXISTS IN LLP.PRE ****
-
- Press ENTER to continue <CR>
-
- /* System returns to Main Menu
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 33 USER'S MANUAL
-
-
-
- OPTION_12_-_CONVERT_WORKING_DAYS_TO_PROJECT_DAYS
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _12_
-
- /* This option creates a calendar of the project's
- life. The start date becomes "Day 1" and each
- succeeding day is assigned a succeeding number.
- The user can request the Project Day for any
- individual day, or he can request a printout of the
- calendar for the entire project.
-
- Enter the name of the input file [.CPM] ? _LLP_
- **** INPUT FILE READ ****
- Enter project length (days) _140_
- **** READING HOLIDAY FILE: LLP.HOL ****
- **** CALCULATING DAYS - TAKES 60 SECONDS ****
- Want a Particular day, Whole printout, or End (P/W/E) _P_
- Enter the project day number _31_
- DAY 31 IS FEB0483
- Want a Particular day, Whole printout, or End (P/W/E) _W_
- **** LLP.DAY HAS BEEN CREATED ****
-
- Press ENTER to continue <CR>
-
- /* System returns to Main Menu.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 34 USER'S MANUAL
-
-
-
-
- OPTION_13_-_GENERATE_CURRENT_COST_REPORT
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _13_
-
- /* This option generates a report of costs expended
- to date based on percentage of completion of each
- activity. The output shows total monies spent per
- activity. An example of the output (contained in
- BASEFILE.CST) is shown in the appendix.
-
- **** PROGRESS COST REPORT ****
-
- Enter the name of the input file [.CPM] _LLP_
- 10 20 30 40 **** INPUT FILE READ ****
- **** FILE LLP.SBC READ - 48 SUBCONTRACTORS READ ****
- Want to suppress Zero-cost activities (Y/N) _Y_
-
- /* Activities for which no costs have been incurred can
- be excluded from the output, if desired.
-
- TOTAL ESTIMATE = 0 AMOUNT EXPENDED = 0
-
- **** LLP.CST HAS BEEN CREATED ****
-
- Press ENTER to continue <CR>
-
- /* System returns to Main Menu.
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 35 USER'S MANUAL
-
-
-
-
- OPTION_14_-_CHANGE_ALL_NODE_NUMBERS
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _14_
-
- /* Option 14 automatically changes node numbers within
- a file. This is useful when project expansion requires
- that new activities be added between existing activities
- where there is no node space available. Option 14 can
- change the existing nodes in two ways:
-
- 1) By multiplying all the nodes by the same integer factor
- 2) An integer number can be selected to be added to all nodes
-
- Either or both methods may be used.
-
- Enter the name of the input file [.CPM] ? _LLP_
- 20 40 **** INPUT FILE READ ****
- **** THIS MODULE ALLOWS YOU TO CHANGE NODES EITHER MATHEMATICALLY
- OR BY USING A [.NDS] FILE SET UP BY OPTION 10 OF THE MAIN MENU ****
-
- Change Mathematically, by [.NDS] File, or Quit (M/F/Q) ? M
- Enter amount to multiply to all nodes _20_
- **** MAXIMUM MULTIPLE IS 1. TRY AGAIN (ENTER 1 FOR NO CHANGE) ****
-
- /* The maximum multiple will vary for each project.
-
- Enter amount to multiply to all nodes _1_
- Enter amount to add to all nodes _0_
- **** FILE LLP.CPM UPDATED ****
-
- Press ENTER to continue <CR>
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 36 USER'S MANUAL
-
-
-
- OPTION_15_-_CONSOLIDATENUPDATEMFILE_TO_INPUT_FILE
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _15_
-
- Enter the name of the input file [.CPM] ? LLP
- 10 20 30 40 **** INPUT FILE READ ****
- File LLP updated - O.K. to write to disk (Y/N) ? Y
- 10 20 30 40 **** FILE LLP.CPM UPDATED ****
-
- /* the system automatically returns to the main menu.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 37 USER'S MANUAL
-
-
-
- OPTION_0_-_EXIT_PCPM_SYSTEM
-
- MENU OF PCPM PROGRAMS
-
- EXIT PCPM SYSTEM - 0
- INFORMATION - 1
- ENTER/CHANGE SUBCONTRACTOR/COMMENT FILE - 2
- ENTER/CHANGE INPUT FILE - 3
- ENTER/CHANGE HOLIDAYS - 4
- PERFORM CRITICAL PATH ANALYSIS - 5
- PERFORM CASH FLOW ANALYSIS - 6
- PRODUCE BAR CHARTS - 7
- SORT OUTPUT - 8
- EXTRACT OUTPUT BY SUBCONTRACTOR - 9
- CHECK NODE NUMBERS - 10
- GET PRECEDENCE OR SUCCEEDENCE DISPLAY - 11
- CONVERT WORKING DAYS TO PROJECT DAYS - 12
- GENERATE CURRENT COST REPORT - 13
- CHANGE ALL NODE NUMBERS - 14
- CONSOLIDATE UPDATE FILES TO INPUT FILES - 15
-
- CHOOSE THE ACTION BY ENTERING THE CORRECT INTEGER _0_
-
-
- EXITING PCPM SYSTEM - GOODBYE FOR NOW
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 38 USER'S MANUAL
-
-
-
- III. IN_CASE_OF_SYSTEM_ERRORS
-
- As many error traps as possible have been included to insure
- efficient usage. However, PCPM does not check every item each
- time in order to keep processing time at a minimum.
-
- If the syStem appears to be "hung up", use the CTRL BREAK keys.
- Enter the system again and check for unconnected nodes, or illegal
- date usage. The most common error is made by editing the data
- files outside the PCPM system and leaving out commas or putting in
- extra data. The simplest solution is to perform editing within
- the PCPM system.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 39 USER'S MANUAL
-
-
-
-
- IV. OUTPUT
-
- After exiting the PCPM system, output can be obtained by following
- the directions for your printer.
-
- A. Primary_Output
-
- Primary output is a list of all activities including
- their estimated duration, actual duration (if completed),
- early and late start times, early and late finish times,
- float, actual reported finish date, and subcontractor
- name (or any comment) associated with the activity.
- There is also a complete listing of all critical path
- activities following the path(s) from start to finish.
- Primary output can be arranged in a variety of sorts by
- utilizing Option 8.
-
-
- B. Cash_Flow_Analysis_Output
-
- This analysis projects monies to be expended on each
- activity during each month of the project.
-
-
- C. Bar_Chart_Output
-
- PCPM outputs a Gantt type bar chart showing the critical
- path, float and activity duration using early start times
- for each activity.
-
- D. Current_Cost_Report
-
- This report shows total costs expended to date for each
- activity based on percentage of project completion.
-
- E. Preceeder_or_Succeeder_Display
-
- This report shows the immediate interrelationships
- between activities - which activity immediately preceeds
- or succeeds any other activity as described by its from
- and to nodes.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- è
- PC PROJECT MANAGEMENT 40 USER'S MANUAL
-
-
-
- V. APPENDIX
-
- A. SAMPLE INPUT FORM
-
- -----------------------------------------------------------
- FROM TO EST REPORT % SUBCONTRACTOR ACT
- DESCRIPTION NODE NODE TIME FINISH DUN CODE (NAME) COST
- -----------------------------------------------------------
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-
- ___________________________________________________________
-